Week #9 - 3-16-09 |
|
|
Work Planned |
Completion Schedule |
| 1. Fairing and body work of front bow |
Completed |
| 2. Sand and prime boot stripe |
Completed |
| 3. Paint boot stripe |
Completed |
| 4. Attach top cap to hull |
Completed |
| 5. Match & spray gelcoat on hull and top cap |
Completed |
| 6. Install interior cabinets |
Completed |
| 7. Install bow rail and deck hardware |
Completed |
| 8. Install rub rail |
Completed |
| 9. Bottom paint |
Completed |
| 10. Buffing & waxing exterior |
Completed |
|
Vessel launched Thursday afternoon 3-19-09 |
|