Week #8 - 3-9-09 |
|
|
Work Planned |
Completion Schedule |
| 1. Fairing and body work of front bow |
Completed |
| 2. Sand and prime boot stripe |
Completed |
| 3. Paint boot stripe |
To be completed 3-11 |
| 4. Attach top cap to hull |
Completed |
| 5. Match & spray gelcoat on hull and top cap |
Completed |
| 6. Install interior cabinets |
To be completed 3-12 |
| 7. Install bow rail and deck hardware |
To be completed 3-15 |
| 8. Install rub rail |
To be completed 3-15 |
| 9. Bottom paint | To be completed 3-15 |
|
Work 1 week behind schedule because the cold weather has interfered with the products drying properly |
|