Week #8 - 3-9-09

   

Work Planned

Completion Schedule

1. Fairing and body work of front bow

Completed

2.  Sand and prime boot stripe

Completed

3.  Paint boot stripe

To be completed 3-11

4.  Attach top cap to hull

Completed

5.  Match & spray gelcoat on hull and top cap

Completed

6.  Install interior cabinets

To be completed 3-12

7.  Install bow rail and deck hardware

To be completed 3-15

8.  Install rub rail

To be completed 3-15

9.  Bottom paint To be completed 3-15
 

Work 1 week behind schedule because the cold weather has interfered with the products drying properly