Week #7 - 3-2-09

   

Work Planned

Completion Schedule

1. Fairing and body work of front bow

Completed

2.  Sand and prime boot stripe

Completed

3.  Paint boot stripe

In Progress

4.  Attach top cap to hull

Completed

5.  Match & spray gelcoat on hull and top cap

In Progress

6.  Install interior cabinets

Not Completed

7.  Install bow rail and deck hardware

Not Completed

8.  Install rub rail

Not Completed

9.  Bottom paint Sanded and prepped, ready for paint
 

Work is likely 1 week behind schedule because the cold weather has interfered with the products drying properly