Week #5 - 2-16-09 |
|
|
Work Planned |
Completion Schedule |
| 1. Finish laying up part & installing DIVINICYL CORE and final laminations |
Completed |
| 2. Pop part from mold, trim & cut off existing plug part from hull |
Part ready to install |
| 3. Pop top cap from mold & build new part | In progress |
| 4. Install new bow and pulpit on hull |
In progress |
| 5. Start to piece top cap together |
Completed |
| 6. Start to compound and wax hull |
Completed |
| 7. Sand and prime boot stripe |
Completed |
| 8. Bottom paint | Sanded and prepped, ready for paint |
|
All work on schedule |
|