Week #2 - 1-26-09 |
|
|
Work Planned |
Completion Schedule |
| 1. Laminate inside of assembled hull flair to hold tight |
Completed |
| 2. Fill in missing sections; fill, fair and shape body work in exterior of hull flair in preparation for mold |
Completed |
| 3. Wax exterior hull flair; laminate exterior for mold; attach bottom portion of bow pulpit to incorporate into hull flair mold |
Completed |
| 4. Start to fabricate new hull flair part after mold is released from hull flair |
Completed |
| 5. Finish hull flair part and cut off existing hull flair to attach newly constructed part |
Completed |
|
|
|
|
|
|
|
All work on schedule |
|