Week #2 - 1-26-09

   

Work Planned

Completion Schedule

1.  Laminate inside of assembled hull flair to hold tight

Completed

2.  Fill in missing sections; fill, fair and shape body work in exterior of hull flair in preparation for mold

Completed

3.  Wax exterior hull flair; laminate exterior for mold; attach bottom portion of bow pulpit to incorporate into hull flair mold

Completed

4.  Start to fabricate new hull flair part after mold is released from hull flair

Completed

5.  Finish hull flair part and cut off existing hull flair to attach newly constructed part

Completed

 

 

 

 

All work on schedule