Week #1 - 1-19-09 |
|
|
Work Planned |
Completion Schedule |
| 1. Construct all scaffolding and planking |
Completed |
| 2. Shrink wrap weather proof tent |
Completed |
| 3. Set up equipment and compressors |
Completed |
| 4. Remove dingy, wrap in plastic and stow |
Completed |
| 5. Remove broken sections of rub-rail and stainless striker rails around bow |
Completed |
| 6. Demo and cut away broken fiberglass pieces |
Completed |
| 7. Remove interior shower cabinetry on port and starboard sides to gain access to interior hull flair |
Completed |
|
All work on schedule |
|