Week #1 - 1-19-09

   

Work Planned

Completion Schedule

1.  Construct all scaffolding and planking

Completed

2.  Shrink wrap weather proof tent

Completed

3.  Set up equipment and compressors

Completed

4.  Remove dingy, wrap in plastic and stow

Completed

5.  Remove broken sections of rub-rail and stainless striker rails around bow

Completed

6.  Demo and cut away broken fiberglass pieces

Completed

7.  Remove interior shower cabinetry on port and starboard sides to gain access to interior hull flair

Completed

All work on schedule